When to Use an RFP

A Request for Proposal (RFP) is the appropriate competitive selection process for purchasing goods or services when price is not the most important criteria to be considered for awarding a contract. The RFP is awarded to the supplier who best meets the qualifications and criteria specified in the RFP. It differs from a Sealed Bid because it allows more flexibility. It may involve negotiating technical requirements, scheduling, type of contract, terms and conditions, and price, including best and final offers. In contrast, a Sealed bid is awarded to the lowest responsible bidder.

What to Include in the Specifications

The department is responsible for providing the Purchasing Office with full and complete specifications for the products or services requested as early in the process as possible. Clearly written and properly organized specifications establish technical goals and administrative and financial expectations as well as set the tone for good communication and a productive relationship between the university and the supplier/contractor. To accomplish this, the specifications must clearly define the user's needs.

Specifications should include the following:

  • Background and purpose for the requested goods or services
  • Scope of work describing the service and/or product including accompanying mandatory and desirable requirements, quantity and units, desired delivery dates or schedules, and technical requirements
  • Clear description of the deliverables to be provided by the supplier
  • Pricing format
  • Basis for evaluation: when specifying requirements, always consider how that requirement will be evaluated and measured
  • Department's plan for monitoring the performance of the supplier

Related Forms

How RFPs are Advertised, Processed, and Awarded

RFPs must be advertised for a minimum of 15 days on the Illinois Procurement Bulletin in order to be in compliance with the Illinois Procurement Code. Additional time may be required for obtaining information as well as preparation by the Purchasing Office.

The formal "RFP opening" is a public opening at the Purchasing Offices. After the RFPs have been opened, they are reviewed by the Purchasing staff, consultation with the State Purchasing Officer and then forwarded to the department for evaluation. The length of time the department needs for the evaluation can vary and may result in meetings with selected respondents and the Purchasing Office for clarification or additional negotiations.

After the evaluation and any additional negotiations are completed, the department submits a letter of recommendation of award to the buyer. The buyer reviews the recommendation and either approves or requests further information from the department.

Once the recommendation is approved by the buyer, and the State Purchasing Officer, the contract is completed and executed, and an award is issued. The award is also advertised in the Illinois Procurement Bulletin.

RFP procurements and awards made pursuant to a competitive bid process are subject to review by the Procurement Policy Board (PPB) and the Commission on Equity & Inclusion (CEI).

Who to Ask

Contact information for the Purchasing offices can be found on the Purchasing & Contract Management About page.